Effingham Boulevard SSO Elimination Project

Special Notes for Residents

Weeks of 7/16 and 7/23 work will be taking place on pavement restoration. Please use caution

Location

This project is on Effingham Boulevard between Sherwood Boulevard and Glenbrook Boulevard

Description

Elimination of a sanitary sewer overflow as well as point repairs to that section of the collection system

Purpose

This USEPA mandated project will eliminate a sanitary sewer overflow in this section of the collection system. The SSO will be removed and point repairs will be made to the rest of the collection system. Once all repairs are completed the system will have a cure in place liner inserted inside to seal off any infiltration. All areas will be restored to what they were previous to the project. The roadway will be resurfaced at project completion.

Inspector

Sue Schmall/Joe Goerndt

Anticipated Completion Date

August 2018

Project Contractor

Trax Construction Company